(Q-1) A project has following characteristic
Activity
|
Preceding activity
|
Expected completion
Time ( in weeks)
|
A
|
None
|
5
|
B
|
A
|
2
|
C
|
A
|
6
|
D
|
B
|
12
|
E
|
D
|
10
|
F
|
D
|
9
|
G
|
D
|
5
|
H
|
B
|
9
|
I
|
C, E
|
1
|
J
|
G
|
2
|
K
|
F, I, J
|
3
|
L
|
K
|
9
|
M
|
H, G
|
7
|
N
|
M
|
8
|
i) Draw a PERT network for this project.
ii) Find the critical path and the project
completion time.
iii) Prepare an activity schedule showing
the ES, EF, LS, LF and slack for each activity.
iv) Will the critical path change if
activity G takes 10 weeks instead of 5 weeks? If so, what will be the new
critical path?
(Q-2). A project with the following six activities is
listed with the normal time period for completion of each activity. Draw the
network diagram and find out the critical path. Also prove that an activity C
is critical activity using early and late start and finish timings.
Activity
|
A
|
B
|
C
|
D
|
E
|
F
|
Immediate Predecessor
|
---
|
A
|
A
|
B
|
C
|
D, E
|
Time Duration
|
4
|
8
|
8
|
5
|
7
|
5
|
(Q-3) What is dummy activity? Why do we need dummy
activities in PERT network? Explain the same in brief and support your answer
with neat sketches.
(Q-4) Find the Shortest path for the given network
below, Where “( )” indicates arc length values.